Reconstruction of the Bridge Street sports ground in Eltham will transform the existing rugby field into a higher performing, more resilient sports surface capable of supporting increased training and match usage.
The Bridge Street Sports ground is currently a low-grade ground, with no established drainage structure and is therefore reliant on surface run-off. Through the winter months the ground becomes water-logged and is regularly closed and usable during the winter season impacting sporting activities.
The project includes new level design implementation, earthworks (cut and fill), drainage and irrigation systems, sand profile installation, installation of Tif Tuf couch turf variety, goal post sleeves, coaches’ boxes and water fountains.
Key components of the project scope include:
The reconstruction is expected to:
The Bridge Street Ground Reconstruction is being funded with:
58 Bridge Street, Eltham 3095 View map
58 Bridge Street , Eltham 3095
Bridge Street
June 2025 LSIF 2025-2026 Funding agreement (EXECUTED)
September 2025Supply and installation of turf tender awarded Lilydale Instant Lawn Pty Ltd
November 2025 Final Plans Completed and endorsed
May 2026Construction tender awarded SJM Turf and Civil Pty Ltd
September 2026Project commencement
June 2027 Expected project completion