Research Park Oval lighting upgrade

  • Project typeFacility upgrade
  • Project value$333,292
  • Project scheduleExpected completion early 2027
research park.png

Background

Research Park Oval is home to Research Junior Football Club and Eltham Collegians Cricket Club. 

The previous sports lighting was installed in 2010-11 at the oval and did not meet requirements for training and games at night and in adverse conditions.

The upgrade project includes a 150 lux LED system to support improved light, energy efficiency and overall improvement to the capability of the facility into the future.

Works include

  • Removal of existing lighting system and poles
  • Installation of four new poles to support the lighting system
  • LED fittings to provide 150 lux levels with shields to manage light spill
  • Upgrade to the power supply and switchboards to support the new system 

Funding details

The Research Park Oval Lighting upgrade is being funded with:

  • $199,975 through the Victorian Government’s 2025-26 Local Sports Infrastructure Fund
  • $30,000 Australian Football League (AFL) grant under the Australian Football Facilities Fund (AFFF)
  • $103,317 Nillumbik Council co-contribution

Location

1459 Main Rd, Research 3095  View map

Google Map